Siva for Kids Foundation got the opportunity to support the reconstruction of a tsunami effected school at Kalmunai, Amapara district, in Sri Lanka. The project is a joined co-operation with international none-govermental organisations like MS Mellemfolkeligt Samvirke (Denmark), 3F Fagligt fælles forbund (Denmark), NST Next Stop Tamils (Denmark) and Green Movement (Sri Lanka).
Mellemfolkeligt Samvirke, the main administrator of this project, has recruited 15 Danish volunteers who will spend their summer holidays in Sri Lanka together with 18 local volunteers, who have been selected by Green Movement. During these three weeks, the 33 young volunteers will rebuild a school near Kalmunai in Ampara district, which was destroid during the tsunami in December 2004.
The brigade participants will work together with local construction workers and during these three weeks they will build a school (architectural drawings and rough budget is attached in the annex).
The brigade will arrive in Kalmunai the 10 th of July 2005 and leave again the 30 th of July 2005. During the workcamp, the brigade participants will be accommodated in a nearby former children's home (which has been moved more inland due to the fear of a new tsunami) and the volunteers will live here in dormitory style.
The Danish volunteers are paying for their plane tickets and for all brigade participants' food and accommodation expenses themselves. The costs have been reduced by donations from the union 3F, but the Danish participants are paying about $ 2000 each in order to cover all the above mentioned expenses.
|
| |
|
|
|
 |
5. BUDGET
- Quantity for the Construction of 80'-X20” School Vishnu School |
|
| |
| No |
Description |
Sri Lankan
Rupees |
| 01. |
Excavation |
|
02. |
Concrete |
|
03. |
Rubble Masonry |
|
04. |
Flooring |
|
05. |
Brick Masonry |
|
06. |
Plaster |
|
07. |
Structural Steel Work
|
|
08. |
Roofing |
|
09. |
Colour washing, Painting & Polishing |
|
10. |
PVC Pipes |
|
12. |
Reinforcements
|
|
13. |
Total
Contingencies – (10%)
|
1,186,694.70
118,669.47
|
| |
Grand Total |
|
|
|
| |
| |
Construction
of Vishnu school at Kalmunai, will begin on 10.07.2005 and duration of this project is 3 weeks, where the process of this reconstruction can be monitored by following . |
|
|